The first question after deciding on a website redesign is "When can we launch?" Agencies answer "It depends", and the plan stays vague.
Timelines are hard to read because the long part is waiting for decisions and materials: copy is late, a decision-maker changes direction, nobody can find the hosting login. That waiting is not in the agency's estimate.
This article splits a redesign into seven phases and covers the time range, deliverables, client and agency roles, and decisions for each. It then looks at why projects slip and how to plan the first 90 days after launch. Whether to redesign at all is covered in 10 Signs You Need a Website Redesign, costs in Website Redesign Cost and How to Read a Quote, URL changes in Website Migration SEO, and CMS changes in Should You Leave WordPress?.
Main sources for this article
- Google Search Central, "Site moves with URL changes" (updated 20 August 2026), plus its guidance on the Change of Address tool and noindex
- The phase definitions in the GOV.UK Service Manual (discovery, alpha, beta, live)
- Nielsen Norman Group articles on usability testing, content audits and tree testing
- W3C's WCAG 2.2 and evaluation guidance, and the European Accessibility Act (Directive (EU) 2019/882)
- The McKinsey and University of Oxford study of more than 5,400 IT projects (2012)
| What you will learn | Short answer |
|---|---|
| What the process looks like | Seven phases plus 90 days after launch (section 1) |
| How long it takes | Partial fix 1–4 weeks, small 2–3 months, medium 3–6 months (section 2) |
| What the client does | Decisions, copy, assets, reviews. The contact needs 2–6 hours a week (sections 10–11) |
| When decisions are made | Four gates: requirements, structure, design, go/no-go (section 12) |
| Why projects slip | Late copy, late decision-makers, scope creep (section 13) |
| What happens after launch | Checks and fixes on day 0, week 1, and days 30, 60 and 90 (section 14) |
1. The phases of a website redesign
Seven phases and 90 days after launch
Agencies name the steps differently, but the work follows much the same path. This article uses seven phases and a post-launch period.
The GOV.UK Service Manual splits service development into discovery, alpha, beta, live and retirement. A redesign is smaller, but the ideas carry over: research before building, test before going live, keep improving afterwards.
| Phase | What happens | Main deliverables | GOV.UK stage |
|---|---|---|---|
| 1. Discovery | Set the goal, measure the current site, count pages | Goal statement, inventory | Discovery |
| 2. Requirements | Agree scope, features and quality standards | Requirements, schedule | Discovery to alpha |
| 3. IA and content | Decide structure, URLs and content owners | Sitemap, content plan | Alpha |
| 4. Design | Lay out screens, create the look, test it | Wireframes, designs | Alpha |
| 5. Build | Set up the CMS, enter copy and images | Site on staging | Beta |
| 6. Testing | Check quality, write the switchover plan | Test log, runbook | Beta |
| 7. Launch | Switch over, redirects, monitoring | Live site, launch log | Live |
The right-hand column is a rough mapping. GOV.UK has larger public services in mind, so borrow the purpose of each stage rather than the names.
A Gantt chart for a medium-sized site
Figure 1 lays out the phases by week for a company site with 20–60 pages in Japanese and English, contact forms and a simple CMS. Phases normally overlap, and when a decision stalls in an overlap, the whole schedule stretches.
Here, launch comes after about 20 weeks (five months). Only about half is work the agency can do alone; the rest includes waiting for client decisions, copy and reviews.
2. How long a website redesign takes
Timeline by project size
There are no official statistics for redesign timelines. The table shows how scope changes the duration. Costs are covered in Website Redesign Cost and How to Read a Quote.
| Scope | Pages and languages | Time to launch | Main reason it runs longer |
|---|---|---|---|
| Partial fix | Some pages or features | 1–4 weeks | Investigating the old system |
| Small rebuild | Up to 20 pages, one language | 2–3 months | Preparing copy |
| Medium | 20–100 pages, two languages | 3–6 months | Translation, number of approvers |
| Large | Features, membership, e-commerce | 6 months+ | Integration with other systems |
Each step up in size roughly doubles the duration, because more people and more decisions are involved, not just more pages. Two languages mean two sets of reviewers; integrations mean working around another team's calendar.
How the time is split across phases
The split across phases follows a pattern whatever the size. The table shows weeks per phase for a small and a medium project.
| Phase | Small (weeks) | Medium (weeks) | Client workload |
|---|---|---|---|
| 1. Discovery | 1–2 | 2–4 | Medium |
| 2. Requirements | 1–2 | 2–4 | High |
| 3. IA and content | 1–3 | 2–4 | High |
| 4. Design | 2–3 | 3–6 | Medium |
| 5. Build | 3–5 | 4–10 | Low to medium |
| 6. Testing | 1–2 | 2–3 | Medium |
Because phases overlap, the total is shorter than the sum. The column to watch is the last one: the client workload peaks in phases 2 and 3. Whether the client can free up time then decides the overall timeline.
3. Phase 1: Discovery
Write the goal in one sentence
The first phase is about finding out, not making. GOV.UK says not to start building during discovery and that there is no set length, though around 4 to 8 weeks is typical. For a company website, 2 to 4 weeks is often enough.
Start by writing the goal in one sentence. "The site looks old" gives you nothing to decide against later. Write something that tells you what success looks like, such as "double enquiries from Europe from 10 to 20 a month" or "fewer people dropping out between the careers page and the application form".
| How the goal is written | Useful for decisions? | How to fix it |
|---|---|---|
| We want a fresh design | No | Say what the new design is for |
| Easier to use on mobile | Partly | Add a metric such as mobile enquiries |
| More enquiries from Europe | Yes | Add the current and target numbers |
| Staff can update the site | Yes | Add how often and who |
Save your current data
To judge whether the new site is better, you need pre-launch figures, and data does not keep forever. Google Search Console's performance data covers the last 16 months; anything older must be exported and stored yourself. In Google Analytics 4, retention for the event-level data used in explorations is set to 2 or 14 months.
| Data to save | Where | Why |
|---|---|---|
| Search impressions and clicks by page and query | Search Console | Compare search performance after launch |
| Page views and enquiries by page | GA4 or similar | Decide which pages to keep or merge |
| Pages with the most inbound links | Search Console links report | Prioritise redirects |
| Speed (Core Web Vitals) | PageSpeed Insights | Set targets for the new site |
| A full list of URLs | Sitemaps, a crawler | The basis of the redirect map |
Take a content inventory
Nielsen Norman Group recommends separating a content inventory (a list of everything) from a content audit (an assessment of its quality). Crawlers and CMS exports can automate the inventory; people review each item in the audit and mark it keep, update or remove.
The same article advises against trying to do everything at once: timebox the work, for example to six weeks, and start with the most-used content. On a site with hundreds of pages, begin with the top pages by traffic and the pages that lead to enquiries, so you can feed into the phase 3 content plan quickly.
4. Phase 2: Requirements
What to decide
Requirements decide what will and will not be built. They become the basis for the quote and the schedule. List quality standards as well as features.
| Area | What to decide | Example |
|---|---|---|
| Scope | Pages, languages, rebuild or migrate | 40 pages, JA/EN, migrate the blog |
| Features | Forms, search, membership, integrations | Contact and brochure request forms |
| CMS and updates | Who updates what, how often | Comms team updates news weekly |
| Quality standards | Speed, accessibility, browsers | WCAG 2.2 AA, LCP under 2.5 s |
| Legal notices | Cookie consent, privacy, company details | EU consent banner |
| Launch date and constraints | Target date, fixed dates | Live two weeks before the trade fair |
Write quality standards as numbers
"A fast site" or "a site anyone can use" cannot be tested before launch. Write standards as numbers or named standards.
For speed, use Google's Core Web Vitals thresholds. web.dev rates a page as good at the 75th percentile of users when LCP (main content displayed) is 2.5 seconds or less, INP (response to input) 200 milliseconds or less and CLS (layout shift) 0.1 or less. web.dev also recommends setting a performance budget, such as limits on image weight and script size, early in the project to avoid backtracking later.
For accessibility, the usual benchmark is level AA of W3C's WCAG 2.2 (published 5 October 2023, updated 12 December 2024). If you sell services such as e-commerce to EU consumers, the European Accessibility Act (EAA, Directive (EU) 2019/882) has applied since 28 June 2025. Services provided by microenterprises, with fewer than 10 staff and annual turnover or balance sheet total of €2 million or less, are excluded. Check whether you are covered during requirements.
| Standard | Example wording | How to test |
|---|---|---|
| Loading speed | LCP 2.5 s or less on the top 5 pages | PageSpeed Insights |
| Responsiveness | INP 200 ms or less | Field data after launch |
| Accessibility | WCAG 2.2 level AA | Automated checks plus manual review |
| Supported environments | Latest two versions of major browsers, 360 px+ | Real devices, dev tools |
| Image weight | 1 MB total per page | Build-time check |
Write requirements and schedule together
Once requirements are set, the agency proposes a schedule. Check that it lists the client's own tasks and deadlines. A schedule showing only agency work has not allowed for waiting on copy and approvals.
Requirements end with the first decision gate ("requirements signed off", section 12). Scope is fixed here, and both sides agree that anything added later is handled as a change.
5. Phase 3: Information architecture and content
Structure and navigation
Information architecture (IA) decides how pages are grouped, ordered and named. Copying the old structure often leaves an outdated org chart in the menu. Rebuild it around what visitors look for: services, prices, case studies, contact.
Nielsen Norman Group describes tree testing, in which participants try to find things in a text-only version of a proposed menu. It needs no design or copy, and NN/g recommends it at the start of a redesign to benchmark the current structure, after a card sort to check the new one, and before content and layouts are created.
| Method | What it tells you | When |
|---|---|---|
| Analytics and search queries | What people actually read and look for | Phases 1–3 |
| Card sorting | How users group and name things | Before drafting the structure |
| Tree testing | Whether people can find things in it | Before fixing the structure |
| Internal interviews | Common enquiry questions, sales materials | Phases 1–3 |
Decide the URL policy
The structure determines the new URLs. If URLs change, start the redirect map (old URL to new URL) in this phase. How to build it and which status codes to use are covered in Website Migration SEO; here we only place it on the schedule.
| Task | Start | Deadline |
|---|---|---|
| List of old URLs | Phase 1 | Before phase 3 |
| New URL policy | Phase 3 | With the structure decision |
| Redirect map | Phase 3 | Mid phase 5 |
| Setting up and testing redirects | Phase 5 | Phase 6 |
Plan the content
Copy is the task most likely to slip. Make a table per page of who writes, who reviews and the deadline. Reused, rewritten and new pages take very different amounts of time.
| Page type | Work | Time per page |
|---|---|---|
| Reused | Update wording and facts | 30 min–1 hour |
| Rewritten | Restructure and rewrite | 2–4 hours |
| New | Interview, write, review | Half a day–2 days |
| Translation | Translate, review by a local reader | 1–2 weeks after copy is final |
Start translation only once the source copy is final. Translating while the Japanese copy is still changing means translating twice. This queue is the main reason bilingual sites take longer.
6. Phase 4: Design
From wireframes to visual design
Design starts with wireframes that fix where information goes, then moves to colour, type and imagery. Starting with visuals means time spent debating colour, and layout problems found late.
| Stage | Check | Do not check yet |
|---|---|---|
| Wireframes | Order of information, user paths, button placement | Colour, photos, fonts |
| Visual design | Brand fit, readability | Fine wording |
| Prototype | Whether people get lost when clicking | Real data |
| After build | Display on real devices, speed | Structure changes |
Test small and repeat
In a 2000 article, Jakob Nielsen of Nielsen Norman Group wrote that testing with five users finds about 85% of usability problems, and that three rounds of five, with fixes between them, beat one round of fifteen. In a redesign, one test at wireframe or prototype stage and one after the build go a long way towards avoiding major rework after launch.
Test with people close to your real customers, not staff. Have European readers test pages aimed at Europe. A structure that seems clear to a Japanese team will not necessarily read the same way to local visitors.
7. Phase 5: Build and content entry
Keep staging out of search
The build happens on a staging environment separate from production. Two common accidents: staging appears in search results, and the fix for that is carried over to the live site.
Google recommends noindex for pages that should not appear in search, but warns that if robots.txt blocks crawling, Google cannot see the noindex rule, and the page can still appear if other sites link to it. The reliable approach is to restrict access to staging, for example with basic authentication.
| Setting | Staging | Production |
|---|---|---|
| Access restriction (auth) | On | Off |
| noindex | Optional | Must be removed |
| robots.txt disallow all | Do not use | Do not use |
| Analytics | Separate from production | Production setup |
| Form recipient | Test address | Real address |
Once the CMS is ready, copy and images go in. Entering content in-house doubles as training for later updates but takes longer. For CMS migrations, see Should You Leave WordPress?.
8. Phase 6: Testing and launch preparation
What to test
Testing has two layers: the agency's internal QA and the client's acceptance testing. The client tests against the standards in the requirements. Anything not written there cannot be passed or failed.
| Test | What to check | Who |
|---|---|---|
| Display | Layout in major browsers and on phones | Agency |
| Functions | Form submission, auto-replies, search | Agency and client |
| Copy | Typos, outdated facts, wrong language | Client |
| Redirects | Each URL forwards as mapped | Agency |
| Speed | Meets the agreed thresholds | Agency |
| Accessibility | Keyboard use, alt text, contrast | Agency and client |
W3C says accessibility problems are easier and cheaper to fix the earlier and more often you evaluate during design and development. No tool alone can tell you whether a site conforms; human review and involving users with disabilities make the evaluation sound.
Before launch day
Finish the switchover preparation before the date. For a move without URL changes, Google recommends lowering the DNS TTL about a week before, and keeping the old server until its traffic reaches zero.
| Preparation | Deadline | Why |
|---|---|---|
| Lower the DNS TTL | About a week before | The switch propagates faster |
| Freeze updates on the old site | A few days before | Prevents old and new content diverging |
| Verify old and new sites in Search Console | Before launch | Needed for monitoring and procedures |
| Write a rollback procedure | Before launch | So you can switch back |
| Draw up a launch-day rota | Before launch | Who checks what |
Finally, hold the fourth decision gate, go/no-go (section 12). If serious defects remain, this is where the launch date moves.
9. Phase 7: Launch day
Running the day
Launch early in a working week, when people can respond for several days in a row. Avoid Friday afternoons and the days before long holidays. Put the day's tasks in a table with times and owners.
| Approx. time | Task | Who |
|---|---|---|
| Morning | Final backup, confirm the freeze | Agency |
| Morning | Switch DNS or server | Agency |
| Right after | Remove noindex and auth, test redirects | Agency |
| Right after | Manually check key pages and forms | Client and agency |
| Afternoon | Submit the new sitemap, check tracking | Agency |
| End of day | Log the day, share next-day checks | Both |
Notifying Google
For moves with URL changes, Google's steps include turning on the redirects, submitting the new sitemap and, for a domain change, using the Change of Address tool in Search Console, whose effect lasts 180 days after you start. Details are in Website Migration SEO.
10. Roles: client and agency
Who does what
Many delays come from tasks nobody owns: copy, photos, domains and legal wording that each side assumes the other is handling.
| Task | Client | Agency |
|---|---|---|
| Goals and success metrics | Decides | Proposes |
| Scope and requirements | Approves | Writes them up |
| Copy | Writes and reviews | Sets structure and length |
| Photos, logos, assets | Supplies | Specifies number and format |
| Design | Approves | Creates |
| Build and testing | Acceptance testing | Builds and tests |
| Domain and DNS | Grants access | Configures |
| Legal wording | Responsible for content | Provides the placement |
How much client time it takes
The client needs at least two roles: a day-to-day contact, who gathers internal views and talks to the agency, and a decision-maker, who makes the final call at the four gates in section 12.
| Role | Phases 1–3 | Phases 4–6 | 90 days after launch |
|---|---|---|---|
| Day-to-day contact | 4–6 h/week | 2–4 h/week | 1–2 h/week |
| Decision-maker | 1–2 h per gate | 1–2 h per gate | 1 h every 30 days |
| Content owner | 4–8 h/week | 1–2 h/week | Depends on update frequency |
| Department reviewers | As needed | A few hours in testing | None |
These are estimates from DevNJ's experience. If the contact has no time, answers are late and the project stretches accordingly. Reducing the contact's other duties for the duration is one of the most effective fixes.
11. What the client needs to prepare
Checklist with deadlines
Here is what the client prepares, in the order it is needed. Account access and copy are the items most likely to stall a phase.
| Item | When needed | Often overlooked |
|---|---|---|
| Goals and success metrics | Phase 1 | Include current figures |
| Access to the current CMS and hosting | Phase 1 | The previous agency may hold it |
| Access to the domain and DNS | Phases 1–2 | Registrant name and renewal date |
| Access to Search Console and analytics | Phase 1 | Tied to a former employee's account? |
| Keep/update/remove decision per page | Phases 1–3 | Agreement between departments |
| Copy, photos, logos | Phases 3–5 | Photo licence scope |
| Legal notices (privacy, company details) | Phase 5 | Check EU pages against local rules |
| Acceptance testers and dates | Phase 6 | Clashes with holidays |
12. When decisions are made
Four gates
A redesign involves many decisions, but the ones that are expensive to reverse come down to four. Place each at a phase boundary, and set the date and the decision-maker at the start.
| Gate | What is decided | Who decides | Cost of reopening it |
|---|---|---|---|
| Requirements | Scope, features, quality standards, launch date | Decision-maker | Re-quote and full reschedule |
| Structure and content plan | Structure, URLs, content owners and deadlines | Decision-maker and contact | Redo design and copy |
| Design | Look and layout of key screens | Decision-maker | Redo the build |
| Go/no-go | Launch or postpone | Decision-maker and agency | Incidents after launch |
Three conditions for gates to work
Setting dates is not enough. Three things need to be in place.
- The decision-maker is involved from the start. An executive who first sees the work at the last gate can reopen every earlier decision.
- Material arrives before the meeting. Otherwise nobody can decide in the room.
- Decisions are written down on one dated page, so "nobody told me" cannot follow.
13. Why redesign projects slip, and what to do
What a study of large IT projects shows
In 2012, McKinsey and the University of Oxford studied more than 5,400 IT projects. Large ones, with initial budgets above $15 million, ran on average 45% over budget and 7% over time, and delivered 56% less value than predicted. A company website redesign is far smaller, so these figures do not transfer directly.
The lesson is that drifting from the goal costs more than lateness. Cutting scope to hit a date can remove the parts that served the goal. When you cut, choose against the one-sentence goal from phase 1.
Common causes of delay
The table lists frequent causes, warning signs, fixes and typical delay. The delay ranges are estimates from DevNJ's experience.
| Cause | Warning sign | Fix | Typical delay |
|---|---|---|---|
| Copy not ready | No named owner | Owner and deadline table in phase 3 | 2–6 weeks |
| Decision-maker joins late | Not present at requirements | Involve them from the first gate | 2–4 weeks |
| Scope creep | More "while we're at it" requests | Move additions to a later stage | 1–8 weeks |
| Missing account access | Nobody knows who the admin is | Collect access in phase 1 | 1–3 weeks |
| Translation queue | Translating before copy is final | Translate after copy is final | 1–3 weeks |
| Integration with other systems | Other side's contact unknown | Confirm their schedule in requirements | 2–8 weeks |
| Too many review rounds | Many approvers | One or two people decide | 1–4 weeks |
Put holidays and busy periods in the plan
When people in Japan and Europe are involved, add both sides' holidays and busy periods to the calendar at the start. Japan's fiscal year-end, Golden Week, Obon and New Year, and Europe's July–August summer holidays and the Christmas to New Year period are when reviews and decisions tend to stall.
14. The first 90 days after launch
Some turbulence is normal
Search traffic can fluctuate after launch. For a move with URL changes, Google says new URLs can take a few weeks or more to replace old ones on a medium-sized site, longer on large ones, and advises keeping redirects for at least a year.
Even for a server-only move, Google calls a temporary drop in crawl rate normal; it usually recovers within days. Do not restructure on the first few days' numbers.
What to watch, and when
For monitoring after a move, Google suggests using the Sitemaps report to track indexing of old and new URLs, the indexing report to confirm the old site declining and the new one growing, the search queries report to see impressions and clicks moving to new URLs, and server logs to spot unexpected errors. The table assigns these to time windows.
| Period | What to watch | Benchmark | Act when |
|---|---|---|---|
| Day 0 to week 1 | 404s, 5xx errors, missing redirects | Zero errors on key pages | Fix the same day |
| Week 2 | Enquiry numbers, form delivery | Close to the same weekdays on the old site | A sharp drop: suspect forms or tracking |
| Day 30 | Impressions, clicks, key page views | An equal period on the old site | One page falls: investigate it |
| Day 60 | URL replacement, field speed data | Old URLs falling, new URLs rising | Check URLs that are not replaced |
| Day 90 | The goal metric (e.g. enquiries) | Progress towards the phase 1 target | Set the order of next fixes |
To avoid seasonal effects, compare with the same period last year or with periods containing the same weekdays. Search Console keeps 16 months of data, so line up your post-launch figures with the data you exported before launch to compare year on year.
What to decide at 90 days
GOV.UK describes the live phase as running a service sustainably while improving it, based on user research and reviewed against the success measures set before going live.
For a redesign, deciding three things at day 90 keeps improvement going.
| Decision | Content | Owner |
|---|---|---|
| Order of improvements | What to do next quarter, in order of impact on the goal | Contact and agency |
| Update routine | Who updates what, how often | Contact |
| Maintenance scope | CMS updates, backups, monitoring contract | Decision-maker |
15. What changes between Japan and Europe
Different working habits
For sites aimed at both Japan and Europe, scheduling habits differ too. Treat these as different conditions, not better or worse, and it becomes easier to align expectations on both sides.
| Item | Common in Japan | Common in Europe |
|---|---|---|
| Quotes and contracts | Fixed lump sum for a defined scope | Hourly rates or phase-by-phase contracts are common |
| Reviews | Documents approved in meetings | Short cycles reviewing working pages |
| Holiday slowdowns | Fiscal year-end, Golden Week, Obon, New Year | July–August, around Christmas |
| Extra legal work | Notices under Japanese commerce law | Cookie consent, EAA, company details |
| Languages | Japanese first, English added later | Multilingual from the start |
Decide early on bilingual sites
For a bilingual site, decide in phase 3 the URL pattern for each language (for example a /en/ folder), how to handle pages that exist in only one language, and who reviews translations. Changing the language structure after launch means changing URLs, which is as much work as another site move.
16. Worked examples (fictional)
The three companies below are fictional and illustrate how scheduling changes with circumstances.
Case A: Japanese manufacturer expanding English pages
Machine-parts maker A has 40 Japanese and 8 English pages and wants 40 in both to win European distributors. With 32 new English pages, copy and translation set the timeline. The key is naming the European reviewer, and checking their summer holiday, during requirements.
Case B: Japanese food shop in the Netherlands adding e-commerce
Shop B in The Hague wants to add e-commerce to a five-page site and sell to EU consumers, so it checks the European Accessibility Act during requirements. With fewer than 10 staff and turnover under the threshold it may be excluded, but building to WCAG 2.2 AA anyway is a reasonable choice.
Case C: Japanese service company with a fixed launch date
Company C must launch in three months for a new service. Medium scope will not fit, so it launches with 10 key pages and adds the rest within 90 days. The redirect map and baseline data are not cut.
| Case | Size | Estimated timeline | Key task |
|---|---|---|---|
| A: More English pages | Medium, two languages | 4–6 months | Copy and translation reviewers |
| B: Adding e-commerce | Small plus e-commerce | 3–5 months | EAA check and payment setup |
| C: Fixed launch date | Medium, phased launch | 3 months + 90 days | Deciding what to launch with |
17. Checklist
Before you start
- The goal is written in one sentence, with a success metric and current figures
- A decision-maker and a day-to-day contact are named, and the contact has time freed up
- Search Console and analytics data are exported and saved
- Access to hosting, domain and CMS is collected
- Both sides' holidays and busy periods are in the calendar
During the project
- Dates and decision-makers are set for the four gates
- Speed and accessibility standards are in the requirements as numbers or named standards
- Content owners and deadlines are in a per-page table
- Translation starts only after copy is final
- Staging has access restrictions
- The redirect map is drafted and redirect testing is scheduled
Launch and after
- Launch is early in the week, with people available for several days
- DNS TTL was lowered about a week before
- noindex and authentication were confirmed removed on launch day
- Checks are scheduled for week 1 and days 30, 60 and 90
- The maintenance contract says redirects stay for at least a year
Summary
- Think of a redesign as seven phases (discovery, requirements, IA and content, design, build, testing, launch) plus 90 days after launch.
- Time to launch is roughly 1–4 weeks for a partial fix, 2–3 months for a small site, 3–6 months for a medium site and 6 months or more for a large one.
- Client workload peaks in requirements and IA/content. Whether the contact has time decides the timeline.
- Set dates and decision-makers up front for the four gates: requirements, structure and content, design, go/no-go.
- Delays cluster around late copy, late decision-makers and scope creep. When cutting scope, choose against the one-sentence goal.
- After launch, allow for Google's few weeks or more on a medium-sized site, and compare against your saved pre-launch figures at 30, 60 and 90 days.
Sources
Google (search and analytics)
- Site moves with URL changes — Google Search Central: move steps, timing, redirects, monitoring (updated 20 Aug 2026)
- Site moves without URL changes — Google Search Central: DNS TTL, old server, crawl rate
- Block search indexing with noindex — Google Search Central: noindex and robots.txt
- Change of Address tool — Search Console Help: 180-day forwarding
- Debugging drops in Google Search traffic — Google Search Central: 16-month comparison, data export
- Introducing the new Search Console — Google Search Central Blog: 16 months of data
- Data retention — Google Analytics Help: GA4 retention of 2 or 14 months
Performance and accessibility
- Web Vitals — web.dev: LCP, INP, CLS thresholds
- Performance budgets 101 — web.dev: setting budgets early
- WCAG 2 Overview — W3C WAI: WCAG 2.2 dates and levels
- Web Content Accessibility Guidelines (WCAG) 2.2 — W3C: success criteria
- Evaluating Web Accessibility Overview — W3C WAI: evaluate early; tools are not enough
- Directive (EU) 2019/882 — EUR-Lex: EAA text, dates, microenterprise exemption
- European accessibility act — European Commission: scope of the EAA
Process and user research
- Agile delivery — GOV.UK Service Manual: the phases
- How the discovery phase works — GOV.UK Service Manual: around 4 to 8 weeks
- How the alpha phase works — GOV.UK Service Manual: 6 to 8 weeks
- How the beta phase works — GOV.UK Service Manual: private and public beta
- How the live phase works — GOV.UK Service Manual: improving after launch
- Why You Only Need to Test with 5 Users — Nielsen Norman Group: five users, about 85% (2000)
- Content Inventory and Auditing 101 — Nielsen Norman Group: inventory and audit
- Tree Testing — Nielsen Norman Group: testing structure
- Delivering large-scale IT projects on time, on budget, and on value — McKinsey: 5,400+ projects, 45/7/56% (2012)
All sources were checked on 25 October 2026. Timeline and effort estimates are based on DevNJ project plans and are not official statistics. Rules and figures change, so check each link for the latest information before you plan.
FAQ
- How long does a website redesign take?
- It depends on scope. A partial fix such as speed or mobile improvements takes 1–4 weeks, a rebuild of about 20 pages in one language 2–3 months, a medium site of 20–100 pages in two languages 3–6 months, and a large site with membership or e-commerce features 6 months or more. These figures run to launch; allow another 90 days for post-launch tuning.
- What are the steps in a website redesign process?
- Seven phases: discovery, requirements, information architecture and content, design, build and content entry, testing and launch preparation, and launch, followed by a 90-day post-launch period. Making four formal decisions at the phase boundaries, on requirements, structure, design and go/no-go, keeps rework down.
- What does the client need to prepare?
- Goals and success metrics, a decision-maker and a day-to-day contact, access to the current CMS, hosting and domain, Search Console and analytics data, a keep/update/remove decision for each page, copy, photos and logos, and the wording of legal notices. Account access and copy are the most common causes of delay, so start on them early.
- What is the most common reason a redesign timeline slips?
- Usually not the build work itself, but waiting for copy, photos and approvals on the client side, and decisions being reopened when a senior decision-maker joins late. Assigning content owners and deadlines by phase 3, involving the decision-maker from the requirements stage, and agreeing how changes are handled before signing are the main fixes.
- What should we do after launch?
- On launch day, test redirects, key pages and forms. For the first one to two weeks, check errors and 404s daily. Google says a site move can take a few weeks or more to be reflected for a medium-sized site, so compare figures with the same period on the old site at 30, 60 and 90 days and decide what to improve next. Keep redirects for at least a year.
- When should we schedule the launch?
- Early in a working week, when the people responsible can respond for several days in a row. Avoid Friday afternoons and the days before long holidays. The Japanese fiscal year-end, Golden Week, Obon, the European summer holidays in July and August, and the Christmas to New Year period are all times when reviews and decisions tend to stall.